CPG H1 Timeline

The current Celo Public Goods budget covers the period from February 1st, 2024, till July 20th, 2024. All tasks and milestones in the proposal have to be completed during this timeframe. Any initiatives taking place outside of this timeframe can not be included in a proposal.

Any resources unallocated by the CPG budget on July 31st, 2024, will be returned to the Celo Community Treasury.

📄 Submission Phase | February 1st - May 31st, 2024

In this phase, proposals can submit their drafts to the

for discussion and feedback. After being up for at least 7 days and incorporating feedback, the proposal can move to the Voting phase.

⚡ Voting Phase | February 16th - May 31st, 2024

In this phase, proposals can be submitted to the CPG Snapshot, and if passed after a voting period of 5 days following the

, move to the execution phase.

🤝 Proposal Execution Phase | February 1st - July 20th, 2024

In this phase, accepted proposals will be funded based on the agreed payment terms and milestones. Any rewards associated with milestones not completed on July 20th will be voided. It is recommended that any unspent resources be sent back to the Celo Community Treasury by July 31st, 2024.